Dozing on Disposal and Make a Trench.

Dozing on disposal    a. Always tidy up and clean the floors disposal.
      b. Make it as high as half a dike safety haul truck tires that perform
          activity in the disposal

     c. Raise the floor disposal as high as 2% (± 3 meters before the embankment).
     d. Bulldozer operating position is always the left of the position damping haultruck location.
     e. Maintain a stable foundation disposal or dumping periphery so as not to vanish,
         slip and sliding / landslides.
     f. Before doing the work material disposal, be sure disposal free of
         material mushy, muddy, shrubs, making it easy to glue with
         waste material.






   Make a trench.

     a. Bulldozer dug a trench with sloping; tilt the blade by placing
         the low end of the blade in the middle of the trench. when the flatness and depth of the blade
         has been reached to return the blade to the flat position.
     b. Digging trenches with bulldozers average: tilt the blade to dig the trenches "V"
         shallow. for the manufacture of a large ditch, gusurlah at an angle of 90 ° from the center line
         trench. after reaching the desired depth, do evictions throughout
         trench base and sides to be flat.


0 opmerkings:

Plaas 'n opmerking