PT Freeport Indonesia Deploying Comprehensive Evaluation

PT Freeport Indonesia held a thorough evaluation following the collapse of a tunnel in the area of ​​the Big Gossan underground mining at Mile 74 district Tembagapura. Geological structure of the tunnel locations were reviewed.
"It must have been no geotechnical investigations at the site, prior to the construction of which began in 1997," said President Director of PT Freeport Indonesia, Rozik B Soetjipto when met reporters at Hotel Rimba Papua, on Saturday (05/18/2013) night. Review, call him, will be made ​​on the basis of geological structure determination of the location of the tunnel construction.
Until now, I Rozik, the cause of the collapse of the tunnel could not be ascertained. He also ensured that a thorough evaluation also includes an underground mine safety facilities. According to him, prior to this incident periodic evaluations are routinely held. Rozik mention every day not less than 3,000 people working in underground mines of PT Freeport Indonesia.
Currently, Rozik said, all activity stopped mining companies. But he would ask workers to restart the treatment. "Maintenance was it like water that must flow. If it is not taken care of it can be dangerous," he said.
www.kompas.com




0 opmerkings: